BeBlood — HRIS transformation (Oracle HCM)

Effort estimation by Monte-Carlo simulation at P80, plus a risk register — replacing a single number with a defensible range.

Role
Estimation & risk
Domain
HRIS
Solution
Oracle HCM
Method
Monte-Carlo, P80

Context

HRIS transformation on Oracle HCM. The question put to the workstream was not "how much does this cost" but "with what confidence can we state that number".

What I did

Effort estimation by Monte-Carlo simulation rather than by summing averages. Each work package is estimated as a range — optimistic, likely, pessimistic — then the model draws thousands of scenarios to produce a distribution of total effort. We report the P80: the effort figure that covers 80% of simulated scenarios.

Alongside it, the workstream risk register: identification, rating, owner and mitigation for each retained risk.

Outcome

A defensible effort range with its confidence level attached, instead of a single number pulled out of a spreadsheet. [TODO: metric] estimated effort and the spread between P50 and P80.

What I took from it

The sum of average estimates is almost always optimistic: it ignores that overruns compound while savings do not. Reporting a P80 rather than a mean changes the conversation with the sponsor — you discuss an accepted level of risk, not a number to negotiate down.